(BIVN) – The Final Environmental Assessment for the intended decommissioning of the Hōkū Ke‘a Observatory on Maunakea has been published. The Final EA comes with a Finding of No Significant Impact.
The University of Hawai‘i at Hilo plans to decommission “the Hōkū Ke‘a Observatory Building, Generator Building, and associated telecommunications and electrical infrastructure and restore the site to the extent practicable,” the document explains. “The deconstruction, removal, and restoration activities would be conducted pursuant to a Site Decommissioning Plan (SDP) that includes a Site Deconstruction and Removal Plan (SDRP) and a Site Restoration Plan (SRP).”
“Use of the site for astronomy purposes would be permanently ended, and no astronomy re-use is contemplated,” the document says. Separate plans are in the works for a new teaching telescope to be installed at a lower elevation on Maunakea, in the Halepōhaku mid-level area.
The document provides this background:
The Hōkū Ke‘a telescope and observatory was built in the 1960s for use by the National Aeronautics and Space Administration (NASA) and the U.S. Air Force. The University of Hawai’i acquired the telescope in 1970. In 2003, the University of Hawaiʻi gave control of the telescope to UH Hilo’s Department of Physics and Astronomy to train undergraduates on the instrument. In 2010, the old 24-inch telescope was replaced by a 36-inch telescope. Although the Hōkū Ke‘a telescope was intended to play a critical role in the educational mission of UH Hilo’s Department of Physics and Astronomy, it did not achieve satisfactory operational performance. UH Hilo ceased operations in 2015 and decided to decommission the telescope as part of the University’s commitment to reduce its footprint at the summit of Maunakea. The mission of decommissioning is to return the site to as close to the original natural form as possible.
The document states the University believes the Proposed Action “would have short-term and temporary impacts during deconstruction and site restoration activities that would be less than significant to biological resources, geology and soils, water resources, air quality, the existing noise environment, traffic and transportation, socioeconomics, public facilities and services, and natural hazards. Best management practices (BMPs) and other measures would be implemented to minimize impacts, as applicable.”
Hōkū Ke‘a occupies approximately a quarter-acre plot in the summit area. “The project area has been divided into two sections: Area A and Area B. Area A contains the Observatory Building and Generator Buildings, as well as telecommunication and electrical infrastructure,” the Final EA explains. “Area B contains telecommunication and electrical infrastructure associated with the Observatory Building and Generator Buildings, as well as the UKIRT observatory and utility building/lunchroom that are not included as part of the proposed project.”
The document states that the Proposed Action, or Alternative 3, includes:
Complete removal of the Hōkū Ke‘a Observatory Building in Area A
- Demolish Hōkū Ke‘a observatory dome
- Remove foundation in its entirety
- Remove underground utilities (cables and conduit) back to the access road between Area A and Area B
Complete removal of the Generator Building in Area A
- Demolish the Generator Building structure
- Remove foundation in its entirety
- Remove underground utilities (cables and conduit) back to the access road between Area A and Area B
Conductor removal in Area B
Restoration in Area A
- Backfill with local native cinder
- Compact excavated areas to allow for continued use for sunset viewing and trailhead access
- Line top of slope with barrier, such as large, local boulders or guardrail
It is expected that site deconstruction and removal would begin in early-June 2023, the Final EA states, “and take approximately five months (through late-September 2023). Site restoration would commence in September 2023 and would take approximately two months and be completed by late-October 2023.”
by Big Island Video News2:06 pm
on at
STORY SUMMARY
MAUNAKEA, Hawaiʻi - The final EA details the plan to remove the Observatory and Generator Buildings - and certain infrastructure - restoring the site "to the extent practicable."